Net Metering Guide

WBSEDCL Net Metering — Step-by-Step for Rooftop Solar

How grid-connected rooftop solar billing works in West Bengal, and the complete journey from application to a running net-metered plant — explained in plain language by a WBSEDCL enlisted solar vendor.

The Basics

How Net Metering Works

Your solar plant generates electricity during the day — your home or business uses it first.

Any surplus flows into the WBSEDCL grid through a bi-directional (net) meter, earning export credits.

At night or during low generation, you draw power from the grid as usual.

Your bill is calculated on the net of imports minus exports — you pay mainly for the difference.

The Process

Six Steps to a Net-Metered Plant

  1. 01

    Application & Feasibility

    A net-metering application is submitted to WBSEDCL with your consumer details and proposed plant capacity for technical feasibility.

  2. 02

    Technical Sanction

    WBSEDCL reviews the application and issues feasibility/technical sanction for the approved capacity at your premises.

  3. 03

    Solar Plant Installation

    The rooftop or ground-mounted plant is installed as per the sanctioned capacity and applicable technical standards.

  4. 04

    Pre-Commissioning Testing

    String, inverter and protection systems are tested; required documents and test reports are prepared for inspection.

  5. 05

    Net Meter Installation & Testing

    WBSEDCL installs and tests the bi-directional meter that records both imported and exported units.

  6. 06

    Synchronization & Commissioning

    The plant is synchronized with the grid, commissioning is recorded, and your billing shifts to net-metering.

Documents Typically Needed

  • Latest WBSEDCL electricity bill (consumer number)
  • Applicant identity and address proof
  • Site/roof details and proposed system capacity
  • Module and inverter specifications with required test certificates
  • Additional statutory approvals for larger systems, where applicable

How Rainbow Enterprise Helps

  • End-to-end net-metering application and paperwork liaison with WBSEDCL
  • System sizing matched to your sanctioned capacity and consumption
  • Installation and testing aligned to DISCOM inspection requirements
  • Support through meter testing, synchronization and commissioning

This guide is a general overview for customer education. Net-metering procedures, eligible capacities and timelines follow WBSEDCL's prevailing regulations and may change — final requirements are confirmed during the application process for your specific connection.